Greetings from Property Settlement Solutions,
Welcome to the dedicated settlement updates page for Belvedere Main Beach.
As the appointed settlement team on behalf of the developer, we are here to guide you through every step of your settlement journey until you receive your keys.
SETTLEMENT SNAPSHOT
VALUATIONS
Anticipated Mid September
PURCHASER INSPECTIONS
Anticipated to commence for some levels Mid- Late September
OCCUPANCY CERTIFICATE
Anticipated Late September/ Early October
TITLES
Anticipated Late September/ Early October
SETTLEMENT
Anticipated for Mid- Late October
LATEST SETTLEMENT UPDATES
September Timing Update
As the builders are completing final touches to the apartments and getting ready to start inspections at Belvedere there have been a few small delys onsite.
For those purchasers requiring finance we anticipate bank valuations to commence week beginning 16th September.
Once your apartment is ready for valuation we will send you an email for you to pass onto your lender so they can order the valuation.
Purchaser Inspections are anticipated to begin week beginning 23rd September.
Once your particular apartment is ready for your inspection we will send you an email with a link to our online booking calendar.
The email will also contain information about how the inspection will run, where to meet and rules on numbers and appropriate footwear that must be worn to access the site.
Please see some new photos below.
August Construction Update
Building
- External Painting: The swing stage painting on all façade faces is nearing completion.
- External Fin Installation: Completed.
- Lifts: Two are operational, with the third set to commence operation shortly.
- Carpark: Initial clean-up and removal of builder storage are complete up to Level B2. Line marking and sealing are in progress on Level B3.
Upper Levels (L5 – 24)
- Windows & Balustrades: Installation is complete up to Level 23.
- Framing & Sheeting: Completed on all levels.
- Kitchen Installation: Currently underway on Level 23.
- Floor Finishes: Generally installed on Level 22.
- Initial Apartment Clean: Completed up to Level 10, with final initial clean on Level 18.
- Apartment Defect Rectification: Ongoing on Level 20.
- Lift Lobby: Carpet installation and final painting are progressing through all levels.
Lower Levels (Ground – L4)
- Painting: Underway on Levels 2 and 3.
- Joinery Installation: In progress.
- Ground Floor Planter Boxes: Ready for landscape installation.
- Porte Cohere: High-level finishes are complete.
- Lobby Glazing and Wall Finishes: Installation ongoing.
- Public Domain Work: Has commenced on Peak Ave.
Pool / Recreation Areas
- Pool Coping: Installed
- Paving complete to BBQ area with pool due to commence.
- Walls and Linings: Completed; painting will begin shortly.
- Planter Boxes / Green Wall: Finished and awaiting plant installation.
Completion
We anticipate reaching Practical Completion and Title Registration by the end of September 2024. Note that this timeline is subject to weather conditions, Council / Certifier inspections and the orderly registration of Strata Title. We will provide further updates to help you prepare for settlement and moving into your apartment at Belvedere.
Utilities| Important Information
SETTLEMENT JOURNEY STAGES
CONSIDER FINANCE OPTIONS
4 months prior to settlement you should start to narrow down what financial options you have to settle.
Will you settle by cash, get a home loan, or maybe a combination?
Should you choose to finance with a loan, we recommend you appoint a broker to assist you with your applications.
VALUATIONS
BEGIN
We'll let you know once your apartment is ready bank valuations will be available, usually there are required as part of your loan application.
For purchasers bringing money into Australia, make sure you have set up an Australian bank account and begin transferring your money.
PURCHASER INSPECTIONS
At this point construction on your new home is almost complete. We will send you an invite to conduct your pre-settlement inspection.
Any defects picked up in your inspection, will be noted and passed to the builder to begin addressing.
PRE-SETTLEMENT PERIOD
Once your inspection is complete the next stage is to wait for the Occupancy Permit and Titles to be issued so settlement can be called.
Your finance, either cash transfer or Bank loan, should be finalised and ready for settlement.
During this time the builder will continue to address any defects where possible.
SETTLEMENT
DAY
Once settlement is called your conveyancer will assist you in preparing for your settlement.
Make sure your loan has been finalised and your cash is ready.
Once your settlement is complete the keys to your new home will be available to collect.
POST
SETTLEMENT
Your settlement has been finalised.
We'll pass on details of the move in process and helpful information so you can get ready for your new home.
Your dedicated Owners corporation/ building manager will now be your point of contact & assist you with settling in to your new home.
SETTLEMENT RESOURCES
YOUR SETTLEMENT CO-ORDINATORS
Katrina Hope
Senior Project Manager
katrina@settlement-solutions.com.au
+61 493 098 241
Proudly presented by
COPYRIGHT PROPERTY SETTLEMENT SOLUTIONS 2024
ALL RIGHTS RESERVED
WWW.SETTLEMENT-SOLUTIONS.COM.AU
Coming Soon