Current Project Status:
Concreting
o Wet Joints to Level 1,3,4.
o Upstand walls to common areas
o External Concrete Stairs on L4 to L5
• High-level services commenced up to level 5:
o Services Rough in GF to L3 100% complete
o L4 to L6 50% roughed in across all services
• Plastering/Framing
o GF and L1 plastering and hanging 90%
o L2 plastering and hanging 85%
o L3 framing completed, and hanging has begun
o L4 and L5 framing at approximately 60%
• Installation of Hebel to L2 balconies completed
• Sarking completed to all exposed areas L2-4. GF 75%
• Battens completed to L3, L4 and L5. L2 commenced
• Corbels painted 100% and Brick rails and tiles complete on external up to:
o North elevation 75%
o East Elevation 65%
o South Elevation 40%
• Window installation 95%, sliding doors 70%. Shrouds installed on to 95%.
• Blockwork completed to basement 1.
• Blockwork and services to risers 100%
• Internal Stairs to GF townhouses 100%
• Waterproofing has commenced.
Upcoming works:
All services completely roughed in, and final sheeting to commence
• Wall framing complete across project.
• Balustrades commenced.
• Brick tiles to be completed and scaffold to be removed.
• Substation fit out.
• External cladding commenced from Ground Floor to Level 2.
• Completion of structure component.
• Crane dismantled
• Wet areas to commence
Please see new photos below.
Project Status:
Level 4 pour 1 slab complete, level 4 pour 2 20% complete with bottom steel installed.
PT completed up to L3; 35% completed Level 4
Precast panel supply and installation – Level 3 completed 80%, Level 4 complete 60%
Level 4 formwork complete
Basements stripped and high-level services commenced
Fire services rough in 80% complete up to basement 1
Hydraulic services rough in 80% complete up to basement 1
Electrical services rough in 50% complete up to basement 1
Upcoming Works:
Completion of remaining level 4 pour and both level 5 pours
Level 5 precast installation pours 1 & 2 commenced
Level 6 slab formwork complete, in-slab penos installed, ready for pour.
Ground floor townhouses high-level services commenced
Ground floor wall set out commenced, sanitaryware in-wall components commenced.
Brick railing progression on North and East elevation along precast
Substation prep works commenced
Waterproofing commenced to balconies
Window installation prep work commenced.
Please see new photos below.
Project Status:
Basement 2, 1 and ground Level concrete pours completed
Currently installing ground floor feature archway precast Currently forming up level 1
By the end of year:
Pour level 1 stab and installing of level 1 precast.
At about 3-4 months before settlement you should start to narrow down what financial options you have to settle.
Will you settle by cash, get a home loan, or maybe a combination?
Should you choose to finance with a loan, we recommend you appoint a broker to assist you with your applications.
Generally 6-8 weeks prior to settlement.
We'll let you know once your apartment is ready bank valuations will be available, usually there are required as part of your loan application.
For purchasers bringing money into Australia, make sure you have set up an Australian bank account and begin transferring your money.
Generally 4-2 weeks prior to settlement
At this point construction on your new home is almost complete. We will send you an invite to conduct your pre-settlement inspection.
Any defects picked up in your inspection, will be noted and passed to the builder to begin addressing.
Once your inspection is complete the next stage is to wait for the Occupancy Permit and Titles to be issued so settlement can be called.
Your finance, either cash transfer or Bank loan, should be finalised and ready for settlement.
During this time the builder will continue to address any defects where possible.
Once settlement is called your conveyancer will assist you in preparing for your settlement.
Make sure your loan has been finalised and your cash is ready.
Once your settlement is complete the keys to your new home will be available to collect.
Your settlement has been finalised.
We'll pass on details of the move in process and helpful information so you can get ready for your new home.
Your dedicated Owners corporation/ building manager will now be your point of contact & assist you with settling in to your new home.